Manchester

Saint-Gobain began connecting  26 Manchester homes to the municipal water lines of Manchester Water Works in October 2016. Although PFOA levels were below the State’s regulatory standard of 70 parts per trillion in the private wells at most of the Manchester homes, Saint-Gobain  agreed to fund the connection of all 26 residences to the municipal water system at NHDES’s request.

(This is a timeline of the project from December 2016 to August 2017. For updates on the project past August 2017, please visit the home page or look for the “Manchester” category in the drop-down menu to the right.)

January 2017 – Water system extension is complete.

December 16, 2016 – Water System Extension is complete. Water services are being installed. Twenty-three of the 26 water services have been installed to date. The plumber is working on connecting the interior plumbing turning on the water. At this time, approximately 16 of the residents are using the public water. Plumbing is anticipated to be complete by December 30.

December 2, 2016 – Twenty-six out of 26 services to the property line have been installed.  Eight services have been installed into the homes and are awaiting or have been approved by the plumbing inspector.