Bedford Waterline Extension Update

Work continues on the waterline design. Pennichuck conducted ledge probes and test pits the week of October 30 to November 3.  Also, Pennichuck is  scheduled to wrap up surveying the week of November 12. This puts Pennichuck on track to finalize the design documents by mid-December, with the expectation that the project will be in position to go out to bid this winter.