Update on Amherst Waterline Extension Project

Water Main Construction
Water main construction began on Monday, October 30th.  The crew expects to complete more than approximately 1,400 linear feet of water main installation on Eastern Avenue through the end of today, Friday, November 3rd.  The crew will work on Saturday, November 4th as well, and plans to complete the main installation on Eastern Avenue by the end of the next week, followed by pressure testing and disinfection.  The water main installation will then progress on Skyline Drive.  A second crew will begin main installation on Douglas and Hickory Drives on Monday, November 6th.    

 Water Service Connections
Depending on location, the service connection contractors will begin on November 6th and November 27th, respectively.    If you are an eligible property owner and have not yet returned your contract paperwork to Pennichuck Water, please do so as soon as possible.